News · Honolulu

Honolulu sets two-day deadline for residential permit reviews

New rules aim to cut construction delays by holding agencies accountable for specific turnaround times.

By Omar Khalil ·

Illustration for: Honolulu sets two-day deadline for residential permit reviews
Illustration generated for this article, not a news photograph.

Homeowners and businesses in Honolulu will face stricter timelines for building permit reviews starting in 2027. The City and County of Honolulu Department of Planning and Permitting (DPP) announced new standards requiring individual residential technical reviews to be completed within two business days. Commercial technical reviews must be finished within 10 business days.

These deadlines apply to every review cycle, including resubmittals. The goal is to reduce the time projects spend waiting for approvals from multiple agencies. Currently, a permit cannot advance until all required reviews are complete, meaning a delay by one agency can stall an entire application.

Mayor Rick Blangiardi stated that the permitting process has long been a source of frustration for residents and developers. He noted that delays drive up costs and slow housing construction. "We are committed to changing that," Blangiardi said. "These new standards set clear expectations, demand greater accountability, and ensure everyone involved in the process shares the same sense of urgency."

DPP Director Dawn Takeuchi Apuna emphasized that the efficiency of the process depends on the slowest review. "We are establishing clear expectations and holding ourselves and our partners accountable for meeting them," Apuna said. She added that the changes aim to eliminate unnecessary delays without compromising public health or safety.

The new rules will apply to DPP’s internal review groups and participating City and State agencies. Private utilities and other external entities involved in coordinated permitting will also work toward these timelines, consistent with their legal responsibilities. Agencies have six months to evaluate their staffing and procedures to ensure they can meet the new expectations.

Starting May 10, 2027, the new standards will become the expected operating performance for participating groups. During the six-month evaluation period, DPP will monitor review times and work with agencies to improve efficiency. The department is also using its HNL Build online system to help applicants track outstanding requirements.

Apuna clarified that the new standards apply to agency review time, not the total time an application spends in the system. Total duration includes time spent by applicants preparing corrections. "One of the biggest misconceptions about permitting is that an application sitting in the system means DPP has been reviewing it that entire time," Apuna said. She explained that permits often move through several rounds of corrections between agencies and applicants.

Applicants and design professionals play a role in reducing delays by submitting complete, code-compliant plans. The DPP uses CivCheck, an AI-assisted plan review technology, to identify potential code deficiencies earlier. The department aims to improve public understanding of who is responsible for the next step in the process.

The review standards are part of a larger effort to modernize Honolulu’s permitting system. The DPP recognizes that technology alone cannot eliminate delays. Consistent review standards and better coordination among agencies are intended to move projects forward while maintaining safeguards for the community.

More News · Report a business · Got a Story?

Get Pensacola Herald in your inboxLocal news for Pensacola and Florida. Free, a few times a week, unsubscribe any time.

Get Pensacola Herald in your inboxLocal news for Pensacola and Florida. Free, a few times a week, unsubscribe any time.